A focused 10-week engagement. Anshul audits the infrastructure and architecture. Rajesh sets up the delivery machine. DevOps joins at week 3 to make the infra recommendations actionable. All 18 tasks complete. Team in rhythm. Month 3 begins with zero ambiguity.
Three resources. No generalists. Each role is precisely matched to the task list — no overhead, no underutilisation. The CTO and Rajesh are active from day one. DevOps joins at week 3 once Anshul has completed the architecture deep-dive and can brief them directly.
Every one of the 18 tasks has a single named owner. No shared or unowned items. This is the same discipline Rajesh will enforce on K&I's own team from week 3 onwards.
| # | Task | Owner | Priority | Delivery |
|---|---|---|---|---|
| Section A — Infrastructure Review & Cloud Assessment | ||||
| A01 | Review current hosting setup — document VPS / cloud / on-prem | Anshul | P0 | Week 1 |
| A02 | Application architecture deep-dive — stack, services, broker APIs | Anshul | P0 | Week 1–2 |
| A03 | Environment parity — dev / staging / prod gap analysis | DevOps | P0 | Week 3–4 |
| A04 | Database query performance audit — slow queries, N+1, indexes | Anshul | P1 | Week 2–3 |
| A05 | WebSocket / streaming infra review — live market data feed | DevOps | P1 | Week 3–4 |
| A06 | Infra cost baseline & forecast — current vs projected at launch | DevOps | P1 | Week 5–6 |
| A07 | Cloud infra improvement recommendations report | Anshul + DevOps | P1 | Week 6–7 |
| Section B — Project Manager Process, Accountability & Team Structure | ||||
| B01 | Workload mapping — current task allocation per engineer | Rajesh | P0 | Week 1 |
| B02 | Identify distraction tasks — findings to CEO only, confidential | Anshul + Rajesh | P0 | Week 2 |
| B03 | Separate roadmaps — Trading vs LAS, independent milestones + DRI | Anshul + Rajesh | P0 | Week 2 |
| B04 | Sprint framework setup — 2-week sprints, planning, retros | Rajesh | P0 | Week 3 |
| B05 | Definition of "done" per feature type | Anshul + Rajesh | P0 | Week 3 |
| B06 | Task ownership map — named DRI for every backlog item | Rajesh | P0 | Week 3 |
| B07 | Feature feasibility & lifecycle mapping — effort, deps, risk | Anshul + Rajesh | P0 | Week 2–4 |
| B08 | Feature prioritisation matrix — revenue × completion × risk | Product Manager | P1 | Month 2 · Wk 5 |
| B09 | Compliance stack ownership — assign Trading feature #18 owner | Product Manager | P1 | Month 2 · Wk 6 |
| B10 | Architectural knowledge documentation — drive K&I engineer | Rajesh + Anshul | P1 | Week 5–8 |